Contractor’s Notes 7-19-11
Hello Everyone,
The crown molding for the first floor has been finished. The carpenters are
now completing the baseboard.
The new Paperstone countertop arrived just a few minutes ago. The fabricator
can pick it up tomorrow and start fabrication. Once he has it installed,
Cliff can install the plumbing and then the Cavaliere can tile the
backsplash.
Cavaliere has been on site tiling this past weekend and this week.
The painters are also on site.
The cabinetry install will be complete by early next week.
The Dutch doors have been installed as well as the hardware.
New Canaan Alarm will be out tomorrow to wire the windows and doors.
We are also looking to lay the stones for the driveway at the end of this
week.
There will be 2 site meetings tomorrow. The first will be at 7am with Jon,
Sam and Trillium. The second will be at 10am with Jon, Anthia, Peter and
Tom.
Barbara and Phyllis, if you need to take pictures, feel free to stop by
whenever works for you.