Contractor’s Notes 3-14-11
Hello Everyone,
I am sorry this is a day late, as I was not feeling well yesterday.
Eaves and soffits are being done this week, as well as some corner boards.
New Canaan Alarm was out and are nearly done roughing.
Electrical, plumbing and HVAC roughing is all coming along.
So, the site meeting is still on for tomorrow at 10am. Jon would like approval for some of the soffit details and the sill.
Anthia, the tile measurements that Fordham is looking for is a measurement that we do once the Dura rock is up. Can they send over a rough sketch like what they did before so our tiler can get a grasp on what is ahead of him?
The oil tank is scheduled to be removed this coming Monday.