Contractor's Notes 11-8-10
Hello Everyone,
What to expect this week:
Monday- the guys completed almost all of the interior demo
Tuesday- they will complete the demo of the garage
Wednesday- they will build the foundation walls from the waste wood from the garage and interior
Thursday and Friday- more foundation work, they will be looking to pour early next week
We spoke to Cliff (plumber) who is getting his numbers together. We also spoke to another radiant floor contractor who can come out tomorrow afternoon to give an estimate. Then we will at least have a comparison.
The windows have been ordered and the exterior doors confirmed. The framing order will be placed at the end of the week.